Skyline Residences, Pune
Problem: Wall finishing delays were pushing handover by 6 weeks.
Solution: Shifted 1.8 lakh sq ft from cement plaster to premium gypsum with dedicated application crews.
Result: Project recovered 34 days and saved INR 42 lakhs in labor + finishing.